Gist of decisions taken in the Part-A of 174th OCC meeting of NRPC

Agenda No. 8: Follow-up of issues from various OCC Meetings - Status update
8.1 Sub-stations likely to be commissioned in next 6 months
a) 400/220 kV, 2x500 MVA Kurukshetra GIS- 220 kV D/c Bhadson (Kurukshetra)- Salempur with HTLS conductor: 1 ckt commissioned on 20.07.2020. 2nd circuit to be commissioned in few days.
b) 400/220 kV, 1x315 MVA Kaithal S/s- 220 kV Kaithal (PG)- Neemrana D/C line commissioned on 04.08.2020.
c) 400/220 kV, 1x315 MVA Sikar S/s- Work order for utilization of 2 No. of bays placed on 13.04.2020. Site survey completed. Target completion: December 2020